POWER PLANTS TO EGYPT

Some logistical key points

  • delivery of equipment and material for two power plants, each with an output of 4.8 GW
  • plants are located in Beni Suef and New Capital
  • roughly 400,000 frt per power plant
  • about 250 heavy lifts
  • project period: 22 months
  • attending and supervising critical heavy lift operations
  • about 6,000 container movements in total

Scope of services

  • Sea- and airfreight from worldwide origins
  • mobilizing of heavy equipment (SPMT's Gantry Systems)
  • heavy transportation and installation of core equipment