LPL transports equipment for two power plants in Egypt


LPL Projects + Logistics will be delivering in the next 22 months equipment and material for two power plants in Beni Suef und New Capital/Egypt. In this project 800,000 frt will be moved which corresponds to 400,000 frt for each power plant. More than 500 heavy lifts are planned as well as about 6,000 container movements. 

LPL takes control of the entire logistic operations, attends and supervises sea- and airfreight from worldwide origins to the construction side in Egypt, the installation of core equipment included. The new established LPL office in Cairo supervises all local operations.

The first gas turbines were already delivered in Adabiyah/Egypt in April.

Goal is to increase Egypt’s energy output by 50 percent. At the end of 2017 both power plants should be completed and start be with energy output in 2018.