Energy I
Generators to China
Logistical Key Points
- Transport von zwei Windturbinen-Generatoren
- two Heavylifts
- Weight per Generator 47 t
Scope of services
- Pre-carriage in the USA by truck
- Sea transport from the US to China
Generators and equipment
Logistical Key Points
- Delivery of equipment and material for two power plants (400.00 FRT/plant)
- 250 Heavylifts between 180-480 t
- Project period: 22 months
- 6.000 Container movements
Scope of services
- Sea- and Airfreight ex worldwide origins
- Logistics project management
- Transport / packaging consulting
- Coordination of approx. 4.000 single shipments
- cargo surveys at various ports
- IT based project monitoring
- placement on foundation
Transformer to Norway
Logistical Key Points
- Transformer 115 t
- Dimensions: 5,695x 4,770 x 4,205 m
Scope of services
- Logistics-/ Project Management
- Road Surveys
- Pre-carriage by truck EXW Germany
- Sea freight to Norway
- Truck transport to power plant
Energy II
Equipment for Plant
Logistical Key Points
- Delivery of Equipment to Saudi Arabia CFR Dammam
- 15 lots (2.370,652 cbm) approx 30 containers
Scope of services
- Pre-carriage to Port of Hamburg
- Seafreight ex Hamburg to Saudi Arabia
Transformers and equipment
Logistical Key Points
- Transport of three transformers (475 MVA) for an Offshore-Windpark in UK
- SPMTs/ Pontons/ Coaster as well as modular trainers were used
- Transport of Equipment by tilt trailer
- Dimensions of each transformer: 9,84 x 5,01 x 4,96 m, weight 241 t